Project overview
BC Housing plans to redevelop the site at 564 Fifth Street by adding close to 200 modern, energy efficient rental apartments.
The redevelopment will include:
- 34 affordable homes with income-based rent replacing the former Sanala Apartments for seniors, families and people living with disabilities
- 167 new rental homes with rents close to market rates for households with low to moderate incomes
- Two buildings, each five storeys tall
- A central courtyard with a playground and shared BBQ area
- 171 underground parking stalls
- 212 bicycle parking spaces
- A shared community amenity space
- Indigenous cultural elements in the building design, arrival plaza, and courtyard
The land at 564 Fifth Street will continue to be owned by BC Housing. All former residents will be supported throughout the redevelopment process.
M'akola Housing Society will manage the homes built in Phase 1.
M'akola provides safe and affordable homes for Indigenous people and families across B.C.
This project is being built on the Traditional and Ancestral Territories of the Snuneymuxw First Nation. M’akola Housing Society will honour the Nation's cultural teachings and Indigenous development strategy.
Learn more about the Provincial Redevelopment Program.
We are committed to keeping you informed as the redevelopment proceeds. We will share updates as they are available.
2026 Phase 1 planning
- July – August 2026: Engagement summary report
- August 19, 2026: Open house, 5:00 p.m. - 7:00 p.m., Bowen Park Complex, Nanaimo
- Open house - Boards
2022 to 2026 Design concept
Between 2022 and 2026, former residents, neighbours, and other community members shared their ideas. Their feedback helped shape the early design and rezoning plan.
This feedback will continue to guide the Phase 1 design.
2023
Draft design concept
2024
Site preparation: demolition of vacant building
2025
Development partner and building operator selection
2026
- Rezoning complete
- Phase 1 Development Permit
2027/2028
- Phase 1 Building Permit
- Start of construction
2030
Expected completion of Phase 1 construction